top of page
Industrial blue boiler units with metal piping

20 MW COCHRAN BOILER — DUNPHY CONTROLS UPGRADE

Specialist commercial and industrial projects by AH Control Ltd.

​

20 MW Cochran boiler — Dunphy control upgrade

​

​Both burners received new ETC 6000 base units and HMIs, full recommissioning and combustion optimisation at approximately 4% O₂ across the firing range. Safety interlocks and site SCADA control were tested.

01-1026.jpg

EMERGENCY STEAM BOILER REPAIR

Out-of-hours emergency response

Autoflame MM MK8 controls replacement

Intermittent boiler shutdowns were stopping production. AH Control identified a faulty voltage conditioner, fitted the site's spare MM MK8 and fully recommissioned the controls, combustion curve, sensors, fuel flow and O₂ trim. Operational and safety checks were completed, restoring steam supply and full production.

03-5931.jpg

INDUSTRIAL GAS PIPEWORK TESTING

Natural gas & biogas

Soundness testing to IGE/UP/1

​AH Control completed pipework volume calculations, soundness testing and emergency shut-off valve checks on both fuels. Both systems passed the tests carried out and the installation was returned to service.